InterContinental Hotel – conference centre
TECHNICAL CONTENT
The purpose of reconstructing the conference unit was to align the design of the freshly constructed Club International community area with the design of the conference unit, in order to create harmony between the two spaces. Within the reconstruction project, the hotel purchased new furniture, replaced the carpets and modernised their lighting system.t.
IMPLEMENTING
The design of the interior was made by an international interior design company. 3E International Kft. provided full engineering services throughout the project.
CURIOSITIES
During the whole project, the hotel’s operation was uninterrupted. A three-shift working system enabled an extremely fast completion; as a result, the reconstruction project was completed in merely four weeks.