Project data:
TECHNICAL CONTENT
In the course of the project, a separate building was executed, which includes an educational hall and a headquarters. On the ground floor of the building, there is a heating kitchen, an exhibition space, general transport functions, water blocks and training rooms. On the first floor, the students’ additional educational facilities and the sanitary blocks were placed. On the second floor, office space, interview rooms and meeting rooms were built.
IMPLEMENTING
3E International was responsible for the technical supervision of the new academy.
Investor: Mercedes-Benz Manufacturing Hungary Kft
Investor website: https://gyar.mercedes-benz.hu/index.php/en/
Location: Kecskemét
Project value: 8.765.000 EUR
Service: Technical supervision
Completion: 2018
Photo: Portfolio.hu