TECHNICAL CONTENT
- 6 pcs waste yard (3 pcs recycling center) design, permitting and construction works
- 114 pcs waste collection stations design, permitting and construction works
- Sopron Waste Sorting and transshipment Centre: 10.000 t / year capacity sorting plant design, permitting and construction works and technology design
- Procurement and set-up of the sorting plant technology 24.000 to/year capacity transshipment station design, permitting and construction works and technology design
- procurement and set-up of the technology 3.000 to/year capacity bio waste composting design, permitting and construction works
IMPLEMENTING
Technical supervision and FIDIC Engineer service of the construction works