Remediation of Berhida industrial park

TECHNICAL CONTENT

  • Toxic metal contaminated subsoil removal: 36,700 tonna
  • In situ deposition 36 100 tonna
  • Construction of remediation system: 4 065 lm drainage ditch,
  • 800 m³ drainage block
  • Water clearing and drain system: gravel drain 2 685 lm , gravel block 4 500 m³
  • Monitoring well system: 20 pcs
  • Maintenace and operation of water purification and drainage system.

IMPLEMENTING

Technical supervision service of the construction works.